LOS ANGELES INTERNATIONAL AIRPORT. AUTOMATED PEOPLE MOVER
The Automated People Mover (APM) is an electric train system on a 2.25 mile elevated guideway with six stations total – three outside the terminal loop and three inside.
LAX anticipates groundbreaking in 2018 and the APM to be fully operational in 2023. Pre-construction activities—such as utility relocations, geotechnical investigations and surveying—will begin in the second quarter of 2018. Construction of the guideway—the elevated track along which the APM will run—will start in Summer-Fall 2019. Late 2019 will see construction begin on the six stations. The first APM car will be delivered in late 2020. Major construction will be complete in mid-2022, at which point extensive testing will begin for several months. The APM will be open for passenger services in early 2023.